1. Flat shovel
2. Wheelbarrow
3. Garden hose with fine spray nozzle
4. Hard garden rake
5. Broad-blade chisel, brick splitter or masonry saw for cutting and fitting the brick (the last two are readily available for rent at your local rental store or brick distributer)
6. Carpenter's level
7. Wood "screed" strip - a 2x4. at least 3' long (used to create a uniform sand bed depth)
8. Electric drill and appropriate size bit (for wood edging only)
9. Trowel
10. Broom
11. Plate compactor (rented)
Step 1
Determining How Much You'll Need
Pavers
1. Determine the square feet (length x width) of the area you want to pave.2. Estimate the number of pavers needed:
For 4"x8" pavers-
4.5 pavers per sq. ft.
For 3 5/8"x7 5/8" pavers-
5.2 pavers per sq. ft.
For 3 3/4"x7 1/2" pavers-
5.1 pavers per sq. ft.
Add 5% extra for chipped or broken pavers.EXAMPLE:A 10' by 20' patio = 200 sq. ft. x 4.5 pavers/sq ft = 900 pavers
An additional 5% (900 x .05) = 45 pavers
Total needed so far = 945 pavers
Typically, you should also include an additional 1 1/2 bricks per linear foot of edge for cutting.
EXAMPLE: linear footage = 10+20+20+10 = 60 linear feet
60 x 1.5 = 90 pavers
945 + 90 = 1035 total pavers need for the job
Edging Material
1. Measure the linear foot of open edges - those not up against a house, curb, driveway, etc. This is the number of feet of edging material you will need. If you plan to edge with brick standing on end (soldier position), calculate one brick for each 4" of edge.2. For wood or rigid plastic edging, plan on one stake for each 2 to 3 feet of edge.
Sand and Crushed Stone
1. The sand and crushed stone you will use in your project are measured in cubic yards (1 cubic yard = 27 cubic feet).2. For any type of paving project, whether patio, walkway or driveway, you will always use a 1" depth of sand.
To determine the number of cubic yards of sand, multiply the square footage by .00309.
EXAMPLE: 200 sq ft patio x .00309 = 0.62 cubic yards of sand3. The amount of crushed stone you will need depends on your type of paving project:
For light duty projects- such as walkways or patios - you will use a 4" depth of crushed stone. To determine the cubic yards of crushed stone needed to create a 4" base, multiply the total square footage by .01235
For heavy duty projects- such as driveways - you will use an 8" depth of crushed stone. To determine the cubic yards of crushed stone needed to create a 8" base, multiply the total square footage by .02469
EXAMPLE: For a 200 square foot patio, you will want a 4" base of crushed stone. 200 sq ft x .01235 = 2.47 cubic yards of crushed stone.
EXAMPLE: For a 200 square foot driveway, you will want an 8" base of crushed stone. 200 sq ft x .02469 = 4.94 cubic yards of crushed stone.(In areas of extreme wetness of severe freeze/thaw, you may need a deeper base. Consult you local brick distributer)
Step 2
Preparing the Area
1. Check with your local utility companies to determine the location of underground lines.2. After you are sure that the area you intend to pave has proper drainage (1/4" per foot slope away from foundations or other permanent structures), outline the area with stakes and string, and be sure to include the width of your edging material.
3. Use a flat shovel to remove only enough sod or dirt to provide a flat, level surface upon which to place the crushed stone base. It is important that the dirt or excess soil that is removed and re-installed should be firmly settled with a plate compactor for an even base.
Step 3
Installing the base
1. After compacting the soil, place the crushed stone base into the excavation. Using a plate compactor, tamp down no more than 4" (depth) base material at one time. This is a critical step - if not done carefully and thoroughly, the bricks will move over time.2. The base material should be slightly damp when compacting.
Step 4
Framing the Borders
1. The border, or edging system, is necessary to insure that your brick paving remains firmly in place and stays beautiful for years. Begin by installing, but not anchoring, your edging. Experiment now with the pattern you've chosen by temporarily laying brick around the edge of the paving. (Note that complex designs, like herringbone, may require significant amounts of cut brick.)2. Once you're satisfied with placement, anchor the edging by driving spikes at least 8" into the base every 2 to 3 feet. For wood edging, drill holes and drive the spikes through the middle of the wood. For brick edging, dig a trench deep enough so that the top edge of the edging brick will be flush with the brick surface of your finished project.
3. One border can remain unanchored until final brick installation to insure a tight fit. Now, remove the bricks you temporarily installed.
Step 5
Installing the Sand Bed
1. For a walkway or other fairly narrow project, use 1" outside diameter pipe or cut two wood strips to the desired height of sand (1"). Place them on either side of the paving area. For a wider project, like a patio, place the strips about 3 feet apart.2. Now, fill the area with sand. The sand can be dampened with a fine mist of water prior to installation to eliminate voids.
3. After you pour the sand, use the pipe or wood strips as rails on which you run your "screed" board to insure a uniform sand depth of 1" (Figure A) . Be careful not to walk in or disturb the leveled sand.
4. Remove the screed rails and fill the indentations with loose sand. Level with a broom or trowel.
Step 6
Laying the Brick Pavers
1. Start at a corner - if possible, one that includes an edge such as a house, curb, sidewalk or other fixed edge. Lay one run of brick from the corner along the two adjacent borders (Figure B). Set the brick on the sand. Don't press or hammer them into place. They should fit snugly with about 1/16" to 1/8" gap between each brick. As you work, be sure to work from the laid brick, not the sand. If you disturb the virgin sand, re-level it with a broom or trowel before laying more brick.2. Continue to lay the brick in your pattern, working from your starting corner to the unanchored edge (Figure C). With the original perimeter brick as a reference, put a string line across the front of your laying edge (every 2 to 3 feet) to maintain alignment (Figure D). If the pattern wanders somewhat, a trowel, screwdriver, or wide-blade putty knife can be used to to make small adjustments. Don't be concerned with small gaps between the paving brick - you'll fill them with sand.
3. Be sure to check the level and alignment of the brickwork frequently during installation.
4. Once all the full brick have been installed up to the final, unanchored edge, cut or saw the remaining brick to complete the bond pattern - but insure that the final edge brick are no smaller that two inches in width.
5. Anchor the final border.
Step 7
Finishing Up
1. Inspect your work, making final adjustments in brick height and joint alignment. Then sweep dry sand into all the joints to lock the brick into place.2. To further set the brick, you may want to use the plate compactor to set the brick and gently tamp it down. If a compactor is used, spread a layer of sand over your pavers to prevent contact between the brick and the compactor.
3. The sand you swept into the joints will gradually settle. You should sweep addtional sand into the joints as necessary over the next few rainstorms until the bricks are fully stabilized.
Relax and Enjoy
(Very unofficially, Step 8)
This is the best part. Take a well deserved rest and feast your eyes on your own creation. You've completed a paving project that will enhance the value of your home and, since brick only looks better with age, you can enjoy for years to come.
For the bricks for your next paving project, and for expert advice and answers to all your questions regarding brick paving, visit your local brick distributer. You'll find them in the Yellow Pages under "Brick."
Brick Industry Association
11490 Commerce Park Drive
Reston, Virginia 20191
Phone: (703) 620-0010
Fax: (703) 620-3928This article was posted by permission of the Brick Industry Association